New Capital Power Plant

New Capital, Cairo, Egypt

This project consists of the design; engineering; fabrication; delivery of materials and equipment; erection; testing; commissioning; startup; and putting into service the New Capital Combined Cycle Power Plant with total capacity 0f 4,800 megawatts at ISO condition. Orascom Construction’s scope includes carrying out all the engineering, procurement, construction (EPC), start-up and commissioning works for the balance of plant.

In addition, Orascom is responsible for all the civil and erection works for the project, which is a partnership in consortium with Siemens.